971106: Data Delays this afternoon (fwd)

NOTE: The nws-changes mailing list is no longer active. The list archives are made available for historical reasons.

     
317 
NOUS42 KWBC 061905
     
SPECIAL NCEP DISCUSSION
CENTRAL OPERATIONS / NCEP / NWS / WASHINGTON DC 
1905 UTC THU NOV 06 1997
     
061910Z  CRAY 3 CAME BACK UP AT 1820Z.  12Z AVN FINISHED INCL. 
MARINE WIND/WAVE GUIDANCE.  12Z MESOETA NOW RUNNING BUT OUTPUT 
WILL BE DELAYED DUE TO WORK TO INSTALL FDDI SWITCH ON CRAYS... 
WHICH BEGAN AT 1905Z AND SHOULD HOPEFULLY BE COMPLETED BY 2030Z... 
AT WHICH TIME NCEP GUIDANCE OUTPUT SHOULD RESUME. 
BUREK/SDM/QAP/NCEP

716 
NOUS42 KWBC 061745

SPECIAL NCEP DISCUSSION
CENTRAL OPERATIONS / NCEP / NWS / WASHINGTON DC 1745 UTC 
THU NOV 06 1997

061745Z  STILL WAITING FOR CRAY 3 TO COME BACK UP BUT 
12Z AVN RAN WELL AND HAS NOW FINISHED ON CRAY 5...THE 
REST OF THE AVN FCST OUTPUT SHOULD BE AVBL SHORTLY.  
12Z MESOETA CANNOT START UNTIL CRAY 3 COMES BACK UP.  
AT THIS POINT IT IS STILL PLANNED TO BRING ALL 3 CRAYS 
OFFLINE IN ORDER TO INSTALL AN FDDI SWITCH
FROM 1830Z UNTIL 2000Z BUT THIS PLANNED OUTAGE MAY BE 
JEOPARDIZED BY THE CURRENT UNPLANNED CRAY OUTAGE!