Subject: GINI Transition -- Final Steps:ISSUED 08/27/07 17:-00 UTC From: ESPCoperations <ESPCoperations@xxxxxxxx> Date: Mon, 27 Aug 2007 13:02:53 -0400 To: _NESDIS OSDPD ESPC OUTAGE Notification <ESPC.Notification@xxxxxxxx> Around 13:05 PM we will be transitioning from Nport1 to Nport3.August 27 - switch from NPORT1 to NPORT3 for primary operations; test NPORT3 transmissions including the four satellite composite available from gp12 - following above test or performed concurrently, test NPORT4 transmissions to BNCF
August 28 - if above tests are successful, have Dale H. come to the WWB to remove remaining network cables from GINI and install on NSOF GINI; at this time, the WWB GINI is decommissioned; after cable installation at NSOF GINI, declare system for primary and back-up operational production and dissemination
Contact Point for Questions: ESPC Operations OCL (Operations Crew Leader), 301-817-3880